Search
Generic filters
Select Page
Street Program 2021 Project Updates
September 09, 2021
Curb Work on Dearborn St.

Project Update (as of 9/10/21)

The projects included in the 2021 Street Program plan are underway. Read below for the latest status on each of the project areas. Please note that this is tentative and is subject to change based on weather and subcontractor coordination.

If you have questions or concerns during construction, please feel free to contact John Belger, Superior Bowen’s Project Manager at 816.301.4834 or Mission’s Project Manager, Brent Morton, at bmorton@missionks.org or Celia Duran, Public Works Director, at cduran@missionks.org or 913.676.8375.

Dearborn Dr. and W. 63rd Terrace:
Curb and gutter has been removed and replaced. (Shown in Photo.)
Asphalt patching is scheduled to begin the week of 9/13.
Stormwater inlet replacement is scheduled to begin on 9/15.
Following this work, the pavement will be replaced with a UBAS treatment (final schedule to be determined -TBD).

53rd Place:
Curb and gutter removal and replacement is nearly complete.
Sump pump discharge pipe has been pulled back from the right-of-way and drainage pipe has been installed.
Asphalt will be milled, followed by asphalt base repair, and a 2-inch mill and asphalt overlay. (Final schedule TBD).

60th Street:
Construction was scheduled to begin on this street first; however, there have been delays from the supplier in manufacturing the stormwater inlets and pipe.
Stormwater pipe and inlet construction is scheduled to begin the week of 9/20.
Following this work, curb and gutter and sidewalk removal and replacement will be scheduled.

Search

Search
Generic filters

News Categories

City Events

Pin It on Pinterest